TAB engineers measuring airflow with a capture hood

On site, the terms TAB and commissioning are often used as if they mean the same thing. They are closely related, but they answer different questions. Mixing them up can leave gaps in a project’s scope, and those gaps usually surface at handover.

What is TAB?

TAB stands for testing, adjusting and balancing. It is the process of measuring air and water flows in HVAC systems and adjusting them so that each part of the building receives the quantity the design calls for.

A TAB engineer will typically:

  • Measure airflow at diffusers, grilles and terminal units.
  • Measure water flow through coils, chillers and pumps.
  • Adjust dampers, balancing valves and fan or pump speeds.
  • Record static pressures, temperatures and motor data.
  • Produce a TAB report comparing measured values with design values.

TAB answers one question: is the right amount of air and water going to the right places? Our air and water balancing service covers this in detail.

What is commissioning?

Commissioning is broader. It is a documented process that verifies complete systems, including their controls, perform as intended under real operating conditions. It starts at design stage and continues through construction, testing and handover.

Commissioning answers a different question: does the whole system do what the owner needs it to do? That includes how equipment starts and stops, how it responds to alarms and failures, and how it interacts with other building systems.

How TAB and commissioning fit together

Think of TAB as a foundation. Functional performance testing during commissioning relies on systems being properly balanced first. If airflow to a zone is wrong, a test of that zone’s temperature control will fail for reasons that have nothing to do with the controls.

In most projects, TAB is carried out as one part of the overall commissioning scope:

  1. Pre-commissioning: installation checks, flushing, pressure and leakage testing.
  2. TAB: measuring and setting air and water flows.
  3. Functional performance testing: verifying sequences, controls and system interactions.
  4. Handover: documentation, training and close-out.

Side-by-side comparison

  • Scope: TAB focuses on HVAC air and water distribution. Commissioning covers HVAC, electrical, fire fighting, plumbing and controls.
  • Timing: TAB happens near the end of installation. Commissioning ideally starts at design stage.
  • Output: TAB produces a balancing report with measured data. Commissioning produces a full record of checklists, test results, deficiencies and close-out.
  • Standards: TAB work commonly follows NEBB or AABC procedures. Commissioning often references ASHRAE guidance alongside the project specification.

What happens if you only do one?

TAB without commissioning can leave you with a well-balanced system that still behaves badly, because nobody verified the control sequences or the interfaces with other systems.

Commissioning without proper TAB means functional tests are carried out on systems that are not delivering design flows, so results are unreliable and problems get blamed on the wrong cause.

Why it pays to use one independent team for both

When the same independent provider handles TAB and commissioning, data flows directly from one stage into the next. Balancing results inform functional testing, issues are traced to their real cause faster, and the handover documentation tells one consistent story.